Compliance Category:Hazardous Waste Management
For those open items, indicate what corrective action is planned and milestones established to correct problems.
Verify that the facility is abiding by state and local hazardous waste requirements.
Verify that the facility is operating according to hazardous waste permits issued by the state or local agencies where approved.
(NOTE: Issues typically regulated by state and local agencies include:
Verify that the actions detailed in compliance agreements are being taken according to the schedule established in the agreements.
Determine if the facility has hazardous waste activities or facilities that are federally regulated, but not addressed in this checklist.
Verify that the facility is in compliance with all applicable and newly issued hazardous waste regulations.
Verify that the individuals designated responsible for hazardous waste storage areas are aware of the precise nature of their responsibilities.
Verify that required training for hazardous waste handling is in personnel file.
- Knowledge of all the constituents of the waste (MSDSs) and whether it is listed in 40 CFR 261
- Laboratory analysis
- Knowledge of materials and processes used
(NOTE: Unidentified waste materials and spilled hazardous materials may have to be disposed of as hazardous waste depending on their constituents or characteristics.)
Discuss with staff how wastes generated on the facility were identified and classified.
Determine if the facility followed EPA criteria for identifying the characteristics of hazardous waste and EPA's listed wastes in 40 CFR 261 (see Appendices A, B, C, and D. Note: The appendices contained in this document are dated. Auditors should consult a current version of the regulations to ensure that accurate lists and other requirements are used for assessments. ).
Determine whether the facility generates, transports, treats, stores, or disposes of any hazardous waste (see Appendices A, B, C, and D for guidance) and the quantity.
Waste documentation must be in facility records (40 CFR 262.40).
(NOTE: The following are examples of solid wastes which are not considered hazardous wastes (40 CFR 261.3 and 261.4(b)):
- Household waste
- Fly ash waste, bottom ash waste, and flue gas emission control waste generated primarily from the combustion of coal or other fossil fuels except for facilities that burn hazardous waste
- Drilling fluids, produced waters and other wastes affiliated with the explorations, development, or production of crude oil, natural gas, or geothermal energy.
- Solid waste which consists of discarded arsenic-treated wood or wood products which fail the test for Toxicity Characteristics for hazardous waste codes 0004 through 0017 and which is not a hazardous waste for any other reason if the waste is generated by persons who utilize the arsenic treated wood and wood products for those materials intended end use
- Petroleum contaminated media and debris that fail the test for Toxicity Characteristic of 40 CFR 261.24 (Hazardous Waste Codes D018 through D043 only) and are required to meet the corrective action regulations under 40 CFR part 280
- Used chlorofluorocarbon refrigerants from totally enclosed heat transfer equipment, including mobile air conditioning systems, mobile refrigeration and commercial and industrial air conditioning and refrigeration systems that use chlorofluorocarbons as the heat transfer fluid in a refrigeration cycle, provided that the refrigerant is reclaimed for further use
- Non-tern plated used oil filters that are not mixed with a listed hazardous waste if these oil filters have been gravity hot-drained using one of the following methods:
-- puncturing the filter anti-drain back valve or the filter dome end and hot-draining
-- hot-draining and crushing
-- dismantling and hot-draining
-- any other equivalent hot-draining method that will remove used oil.)
Verify that all data used for determination, including quality assurance data, is maintained and kept available for reference or inspection.
Verify that for these wastes, the facility can demonstrate that there is a known market or distribution for the material (if relevant) and that they meet the terms of the exclusion or exemption.
Verify that documentation is provided that indicates the material is not a waste or is exempt from regulation.
(NOTE: One example of documentation is contracts showing that a second person uses the material as an ingredient in a production process.)
Verify that if the facility is claiming to recycle material, the equipment for the recycling is actually at the facility and in working order.
- No more than 100 kg (220.46 lb.) of hazardous waste is generated in a calendar month
- Total on-site accumulation does not exceed 1,000 kg (2,204.62 lb.) of hazardous waste
- No more than 1 kg (2.2 lb.) of acute hazardous waste (see Appendix E) is generated in a calendar month
Verify that wastes are either treated or disposed of in an on-site facility or delivered to an off-site TSDF, which is one of the following:
- Permitted under 40 CFR 270
- Operating under interim status
- Authorized to manage hazardous waste by a state with an approved hazardous waste management program under 40 CFR 271
- Permitted, licensed, or registered by a state to manage solid waste
- A facility which does one of the following:
-- beneficially uses or reuses, or legitimately recycles or reclaims its waste
-- treats it waste prior to beneficial use or reuse, or legitimate recycling or reclamation.
(NOTE: If a hazardous waste generator meets the requirements for being a CESQG, it is not required to meet any of the standards outlined in 40 CFR Parts 262 through 266, (except 262.11), 268, and 270.)
(NOTE: If a facility mixes its waste with used oil, the mixture is subject to the requirements in Subpart G of 40 CFR Part 279 if it is destined to be burned for energy recovery.)
(NOTE: Quantities of hazardous and acutely hazardous waste greater than the threshold quantities listed above become subject to the standards for LQGs.)
(NOTE: Even though a CESQG is not legally required to use a manifest or obtain a hazardous waste identification number, many hazardous waste haulers will not transport hazardous waste from a facility without a manifest or ID number.)
Verify that the training program is directed by a person trained in hazardous waste management procedures and that the program includes instruction which teaches facility personnel hazardous waste management procedures relevant to positions in which they are employed.
Although not specified by the regulations, examples of training topics for hazardous waste management procedures could include (but would not be limited to) the following:
- Waste turn in procedures
- Identification of hazardous wastes
- Container use, marking, labeling and on-site transportation
- Manifesting and off-site transportation
- 90 day storage area management
- Personal health and safety and fire safety.
Verify that the training program includes contingency plan implementation and is designed to ensure that facility personnel are able to respond to emergencies including (where applicable):
Verify that new employee training is completed within six months of employment/ assignment.
Verify that an annual review of initial training is provided.
Verify that employees do not work unsupervised until training is completed.
Verify specifically that waste storage area managers and hazardous waste handlers have been trained.
- Job title and description for each employee by name
- Written description of how much training each position will obtain
- Documentation of training received by name.
Determine if training records are retained for three years after employment at the facility.
- Wastes are removed that can be removed using practices commonly employed to remove materials from that type of container (e.g., pouring, pumping, and aspirating) and,
- No more than 2.5 cm (1 in.) of residue remains, or
- If the container is less than or equal to 110 gal. (416.40 L), no more than 3 percent by weight of total container capacity remains, or
Verify that for containers that hold a compressed gas, the pressure in the container approaches atmosphere.
Verify that for a container or inner liner that held an acute hazardous waste listed in Appendix E, one of the following is done:
- It is triple rinsed
- It is cleaned by another method identified through the literature or testing as achieving equivalent removal
- The inner liner is removed.
- Containers are not stored more than two high and have pallets between them
- Containers of highly flammable wastes are electrically grounded (check for clips and wires and make sure wires lead to ground rod or system)
- At least 3 ft. (0.91 m) of aisle space is provided between rows of containers.
(NOTE: Any unidentified contents of solid waste containers and/or containers not in designated storage areas must be tested to determine if solid or hazardous waste requirements apply.)
Verify that correct identification number is used on all appropriate documentation (i.e., manifests).
Verify that no more than 1,000 kg (2,204.62 lb.) of hazardous waste is generated in any calendar month.
Verify that the on-site accumulation time does not exceed 180 days.
(NOTE: For an SQG the accumulation start date begins when the first waste is poured/placed into the waste container, except at satellite accumulation points.)
(NOTE: The 180 day time period is extended to 270 days if the waste must be transported more than 200 miles to a TSDF. This extension does not apply if a TSDF is available within 200 miles and the facility chooses to transport the waste to a more distant TSDF.)
Verify that no more than 6,000 kg (13,227.73 lb.) is allowed to accumulate at the facility.
Verify that containers are marked with the date that accumulation began and the words HAZARDOUS WASTE.
Verify that the containers and the areas where containers are stored meet the requirements outlined in the subsections pertaining to SQG.
(NOTE: Quantities of hazardous and acutely hazardous waste greater than the threshold quantities listed above become subject to the standards for LQGs.)
Verify that exception reports were submitted to the regulatory agency when a signed manifest copy was not received within 60 days of the waste being accepted by the initial transporter.
Verify that exception reports are kept for at least three years.
(NOTE: The requirement to prepare a manifest does not apply if:
- The waste is reclaimed under contractual agreement and:
-- the type of waste and frequency of shipments are specified in the agreement;
-- the vehicle used to transport the waste to the recycling facility and to deliver regenerated material back to the generator is owned and operated by the reclaimer; and
-- the generator maintains a copy of the reclamation agreement for at least three years after termination of the agreement.)
(NOTE: Period of retention of records is extended automatically during the course of any unresolved enforcement action or as requested by the regulatory agency.)
(NOTE: Period of retention of records is extended automatically during the course of any unresolved enforcement action or as requested by the regulatory agency.)
Verify that the following emergency information is posted next to the telephone:
- Name and telephone number of emergency coordinator
- Location of fire extinguishers and spill control materials
- Location of fire alarms (if present)
- Telephone number of fire department.
- Job title and description for each employee by name
- Written description of how much training each position will obtain
- Documentation of training received by name.
Determine if training records are retained for three years after employment at the facility.
- Wastes are removed that can be removed using practices commonly employed to remove materials from that type of container (e.g., pouring, pumping, and aspirating), and
- No more than 2.5 cm (1 in.) of residue remains, or
- If the container is less than or equal to 110 gal. (416.40 L), no more than 3 percent by weight of total container capacity remains, or
- When the container is greater than 110 gal. (416.40 L), no more than 0.3 percent by weight of the total container capacity remains.
Verify that for containers that held a compressed gas, the pressure in the container approaches atmosphere.
Verify that for a container or inner liner that held an acute hazardous waste listed in Appendix E, one of the following is done:
- It is triple rinsed
- It is cleaned by another method identified through the literature or testing as achieving equivalent removal
- The inner liner is removed.
Verify that waste in leaking containers is transferred to a new container or managed in another appropriate manner when necessary.
Verify that handling and storage practices do not cause damage to the containers or cause them to leak.
- Generate extreme heat or pressure, fire, explosion, or violent reaction
- Produce uncontrolled toxic mists, fumes, dusts, or gases in sufficient quantities to threaten human health
- Produce uncontrolled flammable fumes or gases in sufficient quantities to pose a risk of fire or explosions
- Damage the structural integrity of the device or facility
- Threaten human health by any other like means.
(NOTE: Incompatible wastes as listed in Appendix F should not be placed in the same drum.)
Verify that hazardous wastes are not placed in an unwashed container that previously held an incompatible waste or material.
Verify that containers holding hazardous wastes incompatible with wastes stored nearby in other containers, open tanks, piles, or surface impoundments are separated or protected from each other by a dike, berm, wall or other device.
- Containers are not stored more than two high and have pallets between them
- Containers of highly flammable wastes are electrically grounded (check for clips and wires and make sure wires lead to ground rod or system)
Verify that the satellite accumulation point is at or near any point of generation where wastes initially accumulate and is under the control of the operator of the waste generating process.
Verify that the containers are in good condition and are compatible with the waste stored in them and that the containers are kept closed except when waste is being added or removed.
Verify that the containers are marked HAZARDOUS WASTE or other appropriate identification.
(NOTE: See Appendices A, B, C, D, and E for a guidance list of hazardous and acute wastes.)
Interview the shop managers to identify when waste is accumulated in excess of quantity limitations, the following actions are taken:
- The excess container is marked with the date the excess amount began accumulating
- The waste is transferred to a storage area within three days where it will be stored for 180 days or less.
(NOTE: Any unidentified contents of solid waste containers and/or containers not in designated storage areas must be tested to determine if solid or hazardous waste requirements apply.)
- Internal communications or alarm system capable of providing immediate emergency instruction to facility personnel
- A telephone or hand-held two way radio capable of contacting local and emergency responders
- Portable fire extinguishers and fire control equipment, including special extinguishing equipment (foam, inert gas, or dry chemicals)
- Spill control equipment
- Decontamination equipment
Determine if equipment is tested and maintained as necessary to insure proper operation in an emergency.
Verify that sufficient aisle space is maintained to allow unobstructed movement of personnel, fire protection equipment, spill control equipment, and decontamination equipment to any area of the operation.
Review procedures employed by facility management to familiarize police, fire departments, and emergency response teams with the layout of the facility, properties of the waste being handled, and general operations as appropriate for the type of waste and potential need for such services.
Review procedures employed by facility management to familiarize local hospitals with the site and types of injuries that could result in an emergency as appropriate for the type of waste and potential need for such services.
(NOTE: Where state or local authorities decline to enter into arrangements, the facility must document this refusal in the operating record.)
Determine if the facility generates restricted wastes (see Appendix G) by reviewing test results or reviewing procedures employed by facility management where process knowledge was applied in making the waste determinations.
- The EPA hazardous waste code and manifest numbers
- The waste is subject to the LDRs and the constituents of concern for F001-F005 and F039 and underlying hazardous constituents in characteristic wastes, unless the waste will be treated and monitored for all constituents (If all constituents will be treated and monitored, there is no need to put them all on the LDR notice.)
- Whether the waste is a nonwastewater or wastewater
- The subcategory of the waste determination, if applicable
- For hazardous debris, when treating with the alternative treatment technologies provided in 40 CFR 268.45, the contaminants subject to treatment, as described in 268.45(b), and an indication that these contaminants are being treated to comply with 268.45.
- For contaminated soil subject to LDRs provided in 40 CFR 268.49(a), the constituents subject to treatment described in 268.49(d), and the following statement: "This contaminated soil [does/does not] exhibit a characteristic of hazardous waste and is [subject to/complies with] the soil treatment provided in 268.49(c) or the universal treatment standards."
Verify that, for waste or contaminated soil which meets the treatment standard at the original point of generation, the notice includes:
- The EPA hazardous waste code and manifest numbers
- The waste is subject to the LDRs and the constituents of concern for F001-F005 and F039 and underlying hazardous constituents in characteristic wastes, unless the waste will be treated and monitored for all constituents (If all constituents will be treated and monitored, there is no need to put them all on the notice.)
- Whether the waste is a nonwastewater or wastewater
- The subcategory of the waste determination, if applicable
- For contaminated soil subject to LDRs provided in 40 CFR 268.49(a), the constituents subject to treatment described in 268.49(d), and the following statement: "This contaminated soil [does/does not] exhibit a characteristic of hazardous waste and is [subject to/complies with] the soil treatment provided in 268.49(c) or the universal treatment standards."
- Waste analysis data, when available
- The signature of an authorized representative certifying that the waste complies with the treatment standards of 40 CFR 268 (the text of the required certification statement can be found in 40 CFR 268.7(3)(i)).
Verify that, for restricted waste which is subject to an exemption from a prohibition of the type of land disposal used, the notice states that the waste is not prohibited from land disposal and includes:
- The EPA hazardous waste code and manifest number
- Statement that this waste is not prohibited from land disposal
- Waste analysis data, when available
- The date the waste is subject to the prohibition
- For hazardous debris, when treating with the alternative treatment technologies provided in 40 CFR 268.45, the contaminants subject to treatment, as described in 268.45(b), and an indication that these contaminants are being treated to comply with 268.45.
(NOTE: SQGs with tolling agreements are required to comply with notification and certification requirements for the initial shipment of waste subject to the agreement. The SQG will retain an on-site copy of the notification and certification along with the tolling agreement for at least 3 years after the termination or expiration of the agreement.)
(NOTE: SQGs treating hazardous debris under the alternative treatment standards are not required to conduct waste analysis.)
Verify that the plan is kept on-site and:
- The plan is based on a detailed chemical and physical analysis of representative sample of the prohibited waste being treated
- The plan contains all information necessary to treat the wastes in accordance with regulatory requirements including the selected testing frequency
- The plan must be kept in the facility's on-site files and made available to regulatory inspectors.
(NOTE: SQGs with tolling agreements are required to comply with notification and certification requirements for the initial shipment of waste subject to the agreement. The SQG will retain an on-site copy of the notification and certification along with the tolling agreement for at least 3 years after the termination or expiration of the agreement.)
Verify that if the facility has determined whether a waste is restricted using appropriate test methods, the waste analysis data is retained on-site in the files.
Verify that if the facility has determined that it is managing a restricted waste that is excluded from the definition of a hazardous waste or solid waste or exempt from RCRA Subtitle C, a one-time notice is placed in the facility's files stating that the generated waste is excluded.
Verify that a copy of all notices, certifications, waste analysis data and other documentation is kept for at least three years from the date that the waste was last sent to on-site or off-site treatment, storage, or disposal.
Verify that SQGs with tolling agreement retain the agreement and copies of notification and certification for at least three years after the agreement expires.
(NOTE: The prohibition on storage does not apply to hazardous wastes that have met treatment standards.)
Verify that liquid hazardous wastes containing PCBs at concentrations greater than 50 ppm are stored at a site that meets the requirements of 40 CFR 761.65(b) (see Toxic Substances Control Act (TSCA)) and is removed from storage within one year of the date it was first placed into storage.
Verify that the correct identification number is used on all appropriate documentation (i.e., manifests).
- The date upon which accumulation begins is clearly marked and visible for inspection
- The recorded start date indicates no container or tank has been accumulating a hazardous waste longer than 90 days (unless granted a 30 day extension)
- Each container and tank is labeled or marked clearly with the words HAZARDOUS WASTE.
(NOTE: For a generator the accumulation start date begins when the first waste is poured/placed into the waste container, except at satellite accumulation points.)
(NOTE: A generator who meets these standards is exempt from meeting the closure requirements outlined in 40 CFR 265.110 through 265.156, except for 265.111 and 265.114.)
(NOTE: A generator who accumulates hazardous waste for more than 90 days (without an extension), is subject to all TSDF and permitting requirements.)
Verify that copies are kept for three years.
(NOTE: Reporting for exports of hazardous waste is covered under the import/export section of this protocol.)
(NOTE: Periods of retention of records may be extended automatically during the course of any unresolved enforcement action or at the request of the regulatory agency.)
Verify that exception reports were filed with the regulatory agency when a copy of the manifest was not received within 45 days of the waste being accepted by the initial transporter.
Verify that manifests and exception reports are kept for three years.
(NOTE: Periods of retention for reports may be extended automatically during the course of any unresolved enforcement action.)
(NOTE: Periods of retention for reports may be extended automatically during the course of any unresolved enforcement action or at the request of the regulatory agency.)
- Internal communications or alarm system capable of providing immediate emergency instruction to facility personnel
- A telephone or hand-held two way radio capable of summoning emergency assistance
- Portable fire extinguishers and fire control equipment, including special extinguishing equipment (foam, inert gas, or dry chemicals)
- Spill control equipment
- Decontamination equipment
- Fire hydrants or other source of water (reservoir, storage tank, etc.) with adequate volume and pressure, foam producing equipment, or automatic sprinklers, or water spray systems.
Determine if equipment is tested and maintained as necessary to insure proper operation in an emergency.
Verify that sufficient aisle space is maintained to allow unobstructed movement of personnel, fire protection equipment, spill control equipment, and decontamination equipment to any area of the operation.
Review procedures employed by facility management to familiarize police, fire departments, emergency response teams with the layout of the facility, properties of the waste being handled, and general operations as appropriate for the type of waste and potential need for such services.
Review procedures employed by facility management to familiarize the hospital with the site and the types of injuries that could result in an emergency as appropriate for the type of waste and potential need for such services.
(NOTE: Where state or local authorities decline to enter into arrangements, the facility must document this refusal in the operating record.)
Verify that the training program is directed by a person trained in hazardous waste management procedures and that the program includes instruction which teaches facility personnel hazardous waste management procedures relevant to positions in which they are employed.
Although not specified by the regulations, examples of training topics for hazardous waste management procedures could include (but would not be limited to) the following:
- Waste turn in procedures
- Identification of hazardous wastes
- Container use, marking, labeling and on-site transportation
- Manifesting and off-site transportation
- 90 day storage area management
- Personal health and safety and fire safety
Verify that the training program includes contingency plan implementation and is designed to ensure that facility personnel are able to respond to emergencies including (where applicable):
- Key parameters for automatic waste feed cut-off systems
- Procedures for using, inspecting, repairing, and replacing emergency and monitoring equipment
- Operation of communications and alarm systems
- Response to fire or explosion
- Response to groundwater contamination incidents
- Response to leaks or spills
- Shutdown of operations.
Verify that new employee training is completed within six months of employment/ assignment.
Verify that an annual review of initial training is provided.
Verify that employees do not work unsupervised until training is completed.
Verify specifically that waste storage area managers and hazardous waste handlers have been trained.
- Job title and description for each employee by name
- Written description of how much training each position will obtain
- Documentation of training received by name.
Determine if training records are retained for three years for former employees.
Determine if training records on current employees are maintained. (NOTE: Training records on current employees must be maintained until the closure of the facility.)
Verify that the contingency plan is designed to minimize hazards to human health or the environment from fires, explosions, or any unplanned sudden or non-sudden release of hazardous waste or hazardous waste constituents.
Verify that the plan includes the following:
- A description of actions to be taken during an emergency
- A description of arrangements made with local police departments, fire departments, hospitals, contractors, and state and local emergency response teams as appropriate
- Names, addresses, and phone numbers of all persons qualified to act as emergency coordinator (if more than one name is listed, the plan must identify one person as the primary emergency coordinator with other persons listed in the order in which they will assume responsibility as an alternate)
- A list of all emergency equipment at the facility and where this equipment is required, located, and what it looks like
- An evacuation plan for facility personnel where there is a possibility evacuation would be needed.
Verify that copies of the contingency plan and all revisions are maintained at the facility and also have been submitted to organizations which may be called upon to provide emergency services.
Verify that the contingency plan is routinely reviewed and updated, especially when:
Verify that the emergency coordinator is thoroughly familiar with the facility, including all operations and activities at the facility, the location of all records within the facility, the facility layout, the characteristics of the waste handled, and the provisions of the contingency plan. In addition, verify the emergency coordinator has the authority to commit the resources needed to carry out the contingency plan.
- Immediately activate facility alarms or communication systems and notify appropriate facility, state, and local response parties
- Identify the character, exact source, amount, and a real extent of any released materials
- Assess possible hazards to human health or the environment, including direct and indirect effects (e.g., release of gases, surface runoff from water or chemicals used to control fire or explosions, etc.)
-- stop processes and operations at the facility when necessary to prevent fires, explosions, or further releases
-- collect and contain the released waste
-- remove or isolate containers when necessary
- Monitor for leaks, pressure buildup, gas generation, or ruptures in valves, pipes, or other equipment whenever appropriate
- Ensure that all emergency equipment is cleaned and fit for its intended use before operations are resumed
- Notify EPA, and appropriate state and local authorities that the facility is in compliance with 40 CFR 265.56(h) before operation resumes.
Verify that written reports have been submitted to the regulatory agency within 15 days after the incident.
- Wastes are removed that can be removed using practices commonly employed to remove materials from that type of container (e.g., pouring, pumping, and aspirating), and
- No more than 2.5 cm (1 in.) of residue remains, or
- If the container is less than or equal to 110 gal. (416.40 L), no more than 3 percent by weight of total container capacity remains, or
- When the container is greater than 110 gal. (416.40 L), no more than 0.3 percent by weight of the total container capacity remains.
Verify that for containers that held a compressed gas, the pressure in the container approaches atmosphere.
Verify that for a container or inner liner that held an acute hazardous waste listed in Appendix E, one of the following is done:
- It is triple rinsed
- It is cleaned by another method identified through the literature or testing as achieving equivalent removal
- The inner liner is removed.
Verify that the rinse water has been tested.
Verify that waste is transferred to a new container or managed in another appropriate manner when necessary.
Verify that handling and storage practices do not cause damage to the containers or cause them to leak.
- Generate extreme heat or pressure, fire, or explosion, or violent reaction
- Produce uncontrolled toxic mists, fumes, dusts, or gases in sufficient quantities to threaten human health
- Produce uncontrolled flammable fumes or gases in sufficient quantities to pose a risk of fire or explosions
- Damage the structural integrity of the device or facility
- By any other like means threaten human health or the environment
(NOTE: Incompatible wastes, as listed in Appendix F, should not be placed in the same drum.)
Verify that hazardous wastes are not placed in an unwashed container that previously held an incompatible waste or material.
Verify that containers holding hazardous wastes incompatible with wastes stored nearby in other containers, open tanks, piles, or surface impoundments are separated or protected from each other by a dike, berm, wall, or other device.
- Containers are not stored more than 2 high and have pallets between them
- Containers of highly flammable wastes are electrically grounded (check for clips and wires and make sure wires lead to ground rod or system)
- At least 3 ft. (0.91 m) of aisle space is provided between rows of containers.
- The average VO concentration of the hazardous waste at the point of waste origination is less than 500 ppmw
- The organic content of the hazardous waste entering the waste management unit has been reduced by an organic destruction or removal process
- The waste meets the numerical concentration limits for organic hazardous constituents as specified in 40 CFR 268.40 or has been treated by the treatment technology established by the regulatory agency for the waste in 268.42(a) or an equivalent method approved by the regulatory agency pursuant to 268.42(b).)
(NOTE: These requirements do not apply to a container that has a design capacity less than or equal to 0.1 m 3 [~26 gal.] (40 CFR 265.1080(b)(2)) or to containers of any size at satellite accumulation points.)
(NOTE: Standards for containers used in waste stabilization processes (40 CFR 265,1087(b)(2)) are in checklist item HW.59.)
Verify that, for containers with a design capacity greater than 0.1 m 3 [~26 gal.] and less than or equal to 0.46 m 3 [~122 gal.], air emissions are controlled according to the following Container Level 1 standards:
- A container that meets applicable U.S. DOT regulations on the packaging of hazardous materials for transportation
- A container that is equipped with a cover and closure devices that form a continuous barrier over the container openings so that when the cover and closure devices are secured in the closed position there are not visible holes, gaps or other open spaces into the interior of the container
- An open-top container in which an organic vapor suppressing barrier is placed on or over the hazardous waste in the container so that no hazardous waste is exposed to the atmosphere.
Verify that when a container using Level 1 standards, other than DOT approved containers, is used, it is equipped with covers and closure devices composed of suitable materials to minimize exposure of the hazardous waste to the atmosphere and to maintain the equipment integrity for as long as it is in service.
Verify that, whenever waste is in a container using Level 1 controls, covers and closure devices are installed and closure devices are secured and maintained in the closed position except as follows:
- Opening of a closure device or cover is allowed for adding waste or other material to the container as follows:
-- when the container is filled to the intended final level in one continuous operation, the closure device is secured in the closed position and the cover is installed at the conclusion of the filling operation
-- when discrete batches or quantities of material are added intermittently to the container over a period of time, the closure devices are secured in the closed position and covers installed upon either the container being filled to the intended final level, the completion of a batch loading after which no additional material will be added to the container within 15 minutes, the person performing the loading operation leaving the immediate vicinity of the container, or the shutdown of the process generating the material being added to the container, whichever condition occurs first.
- Opening of a closure device or cover is allowed for removing the hazardous waste as follows:
-- in order to meet the requirements for an empty container
-- when discrete quantities or batches of material are removed from the container but the container is not empty, the closure devices will promptly be returned to the closed position and the covers installed upon completion of batch removal after which no additional material will be removed within 15 minutes or the person performing the unloading leaves the immediate vicinity, whichever condition occurs first
- Opening of a closure device or cover is allowed when access inside the container is needed to perform routine activities other than transfer of hazardous waste
- Opening of a spring loaded, pressure vacuum relief valve, conservation vent, or similar type of pressure relief device which vents to the atmosphere is allowed during normal operations for the purpose of maintaining internal container pressure
- Opening of a safety device to avoid unsafe conditions.
- The average VO concentration of the hazardous waste at the point of waste origination is less than 500 ppmw
- The organic content of the hazardous waste entering the waste management unit has been reduced by an organic destruction or removal process
(NOTE: These requirements do not apply to a container that has a design capacity less than or equal to 0.1 m 3 [~26 gal.] (40 CFR 265.1080(b)(2)) or to containers of any size at satellite accumulation points.)
(NOTE: Standards for containers used in waste stabilization processes (40 CFR 265.1087(b)(2)) are in checklist item HW.59.)
Verify that, for containers with a design capacity greater than 0.46 m 3 [~122 gal.] that are not in light material service, air emissions are controlled according to the following Container Level 1 standards:
- A container that meets applicable U.S. DOT regulations on the packaging of hazardous materials for transportation
- A container that is equipped with a cover and closure devices that form a continuous barrier over the container openings so that when the cover and closure devices are secured in the closed position there are not visible holes, gaps or other open spaces into the interior of the container
- An open-top container in which an organic vapor suppressing barrier is placed on or over the hazardous waste in the container so that no hazardous waste is exposed to the atmosphere.
- A container is used that meets applicable U.S. DOT regulations on the packaging of hazardous materials for transportation
- A container is used that operates with no detectable organic emissions
- A container is used that has been demonstrated within the preceding 12 months to be air tight.
(NOTE: Level 2 standards apply only to containers that are in light material service. For the containers that are not in light material service, Level 1 standards apply. (See 40 CFR 265.1087(b)(ii) and (iii).)
Verify that when a container using Level 1 standards, other than DOT approved containers, is used it is equipped with covers and closure devices composed of suitable materials to minimize exposure of the hazardous waste to the atmosphere and to maintain the equipment integrity for as long as it is in service.
Verify that whenever waste is in a container using Level 1 or Level 2 controls, covers and closure devices are installed and closure devices are secured and maintained in a closed position except as follows:
- Opening of a closure device or cover is allowed for adding waste or other material to the container as follows:
-- when the container is filled to the intended final level in one continuous operation, the closure devices are secured in the closed position and the covers installed at the conclusion of the filling operation
-- when discrete batches or quantities of material are added intermittently to the container over a period of time, the closure devices are promptly secured in the closed position and covers installed upon either:
--- the container being filled to the intended final level
--- the completion of a batch loading after which no additional material will be added to the container within 15 minutes
--- the person performing the loading operation leaving the immediate vicinity of the container
--- the shutdown of the process generating the material being added to the container, whichever condition occurs first
- Opening of a closure device or cover is allowed for removing the hazardous waste as follows:
-- in order to meet the requirements for an empty container
-- when discreet quantities or batches of material are removed from the container but the container is not empty, the closure devices are promptly secured in the closed position and the covers installed either:
--- upon completion of batch removal after which no additional material will be removed within 15 minutes
--- the person performing the unloading leaves the immediate vicinity, whichever condition occurs first
- Opening of a closure device or cover is allowed when access inside the container is needed to perform routine activities other than transfer of hazardous waste
- Opening of a spring loaded, pressure vacuum relief valve, conservation vent, or similar type of pressure relief device which vents to the atmosphere and is allowed during normal operations for the purpose of maintaining internal container pressure
- Opening of a safety device to avoid unsafe conditions.
- The average VO concentration of the hazardous waste at the point of waste origination is less than 500 ppmv
- The organic content of the hazardous waste entering the waste management unit has been reduced by an organic destruction or removal process
- The waste meets the numerical concentration limits for organic hazardous constituents as specified in 40 CFR 268.40 or has been treated by the treatment technology established by the regulatory agency for the waste in 268.42(a) or an equivalent method approved by the regulatory agency pursuant to 268.42(b).)
(NOTE: These requirements do not apply to a container that has a design capacity less than or equal to 0.1 m 3 [~26 gal.] (40 CFR 265.1080(b)(2)) or to containers of any size at satellite accumulation points.)
(NOTE: Safety devices may be installed and operated as necessary.)
Verify that containers with design capacities greater than 0.1 m 3 [~26 gal.] used for the treatment of a hazardous waste by a stabilization process meet the following Container Level 3 standards at those times during the waste stabilization process when the hazardous waste in the container is exposed to the atmosphere:
Verify that the facility has a written plan and schedule for performing inspections and monitoring.
Verify that the plan and schedule are being met.
Verify that inspections of the containers and their covers and closure devices for containers using Container Level 1 or Level 2 controls are done as follows:
Verify that when a defect is detected, the first efforts at repairs are within 24 hours after detection, and repair is completed as soon as possible but no later than 5 calendar days after detection.
(NOTE: If repair cannot be completed within 5 calendar days, the hazardous waste must be removed from the container.)
Verify that a copy is available of the procedure used to determine that containers with a capacity of 0.46 m 3 [~122 gal.] or greater which do not meet DOT standards are not managing hazardous waste in light material service.
Verify that if using Container Level 3 air emissions controls, the facility prepares and maintains records that:
Verify that if using a closed-vent system and control device, the following records are maintained:
-- a description of the planned routine maintenance that is anticipated to be performed for the control device during the next 6-month period, including the type of maintenance needed, planned frequency, and lengths of maintenance periods.
-- a description of the planned routine maintenance that was performed for the control device during the previous 6-month period, including the type of maintenance performed and the total number of hours during those 6-months that the control device did not meet applicable requirements
-- the occurrence and duration of each malfunction of the control device system
-- the duration of each period during a malfunction when gases, vapors, or fumes are vented from the waste management unit through the closed-vent system to the control device while the control device is not properly functioning
-- actions taken during periods of malfunction to restore a malfunctioning control device to its normal or usual manner of operation
-- records of the management of the carbon removed from a carbon adsorption system.
Verify that, for exempted containers, the following records are prepared and maintained as applicable:
Verify that, for containers not using the air emissions controls specified in 40 CFR 265.1085 through 265.1088 (see checklist items HW.57 through HW.62), the following information is maintained:
-- a facility identification number for the container or group of containers
-- the purpose and placement of this container or group of containers in the management train of this hazardous waste
-- the procedures used to ultimately dispose of the hazardous waste handled in the containers
Verify that all records, except design information records, are kept for at least 3 years.
Verify that design information records are maintained in the operating record until the air emissions control equipment is replaced or otherwise no longer in service.
(NOTE: See also the recordkeeping requirements for carbon adsorption units in checklist item HW.65.)
- The average VO concentration of the hazardous waste at the point of waste origination is less than 500 ppmw
- The organic content of the hazardous waste entering the waste management unit has been reduced by an organic destruction or removal process
(NOTE: These requirements do not apply to a container that has a design capacity less than or equal to 0.1 m 3 [~26 gal.] (40 CFR 265.1080(b)(2)) or to containers of any size at satellite accumulation points.)
Verify that closed-vent systems meet the following:
-- a flow indicator is installed, calibrated, maintained, and operated at the inlet to the bypass line used to divert gases and vapors from the closed-vent system to the atmosphere at a point upstream of the control device inlet
-- a seal or locking device is placed on the mechanism by which the bypass device position is controlled when the bypass valve is in the closed position so that the bypass device cannot be opened without breaking the seal or removing the lock.
Verify that the seal or closure mechanism is visually inspected at least once every month.
Verify that one of the following control devices are used:
Verify that, when a closed-vent system and control device is used, the following are met:
Verify that, if a control device other than a thermal vapor incinerator, flare, boiler, process heater, condenser, or carbon absorption system is used, the requirements in 40 CFR 265.1033(i) are met (see checklist item HW.64).
Verify that, for control devices, it is demonstrated by either a performance test or a design analysis that the device achieves compliance except for the following:
Verify that the readings from each control device are inspected at least once each operating day to check control device operation.
Verify that one of the following is met:
(NOTE: A process vent is not subject to these standards if the facility owner/operator certifies that all the regulated process vents at the facility are equipped with and operating air emission controls in accordance with the requirements of the Clean Air Act (CAA) 40 CFR Parts 60, 61, and 63.)
Verify that control devices involving vapor recovery are designed and operated to recover organic vapors vented to the air with an efficiency of 95 weight percent or greater, unless the total organic emission limit can be attained at an efficiency of less than 95 weight percent.
Verify that, if an enclosed combustion device is used (i.e., vapor incinerator, boiler, or process heater), it is designed and operated to reduce the organic emissions vented to it by 95 weight percent or greater, to achieve a total organic compound concentration of 20 ppmv expressed as the sum of the actual compounds, not carbon equivalents, on a dry basis corrected to 3 percent oxygen, or to provide a minimum residence time of 0.50 seconds at a minimum temperature of 760 degrees Celsius [1400 degrees Fahrenheit].
Verify that, if a boiler or process heater is used as the control device, the vent stream is introduced into the flame zone of the boiler or process heater.
Verify that, if flares are used:
Verify that each monitor and control device is inspected on a routine basis.
-- a temperature monitoring device equipped with a continuous recorder for a thermal vapor incinerator
-- a temperature monitoring device equipped with a continuous recorder for a catalytic vapor incinerator
-- a heat sensing monitor with a continuous recorder for flares
-- a temperature monitoring device equipped with a continuous recorder to measure parameters that indicate good combustion operating practices are being used for a boiler or process heater having a design heat input capacity less than 44 MW
-- for a condenser, one of the following:
--- a monitoring device with a continuous recorder to measure the concentration level of the organic compound in the exhaust vent stream from the condenser
--- a temperature monitoring device equipped with a continuous recorder capable of monitoring temperature in the exhaust vent stream from the condenser with an accuracy of +/- 1 percent of the temperature being monitored in Celsius or in +/-0.5 o C, whichever is greater
-- for a carbon absorption system such as a fixed carbon bed absorber that regenerates the carbon bed directly in the control device, one of the following:
--- a monitoring device equipped with a continuous recorder to measure the concentration levels of the organic compounds in the exhaust vent stream from the carbon bed
--- a monitoring device equipped with a continuous recorder to measure a parameter that indicates the carbon bed is regenerated on a regular, predetermined time cycle.
Verify that readings from monitoring devices are checked at least once a day.
Verify that, if a carbon absorption system is being used that regenerates the carbon bed directly on-site, the existing carbon in the control device is replaced with fresh carbon at a regular, predetermined time interval.
(NOTE: The predetermined time interval is based on the design analysis required under 40 CFR 265.1035(b)(4)(iii)(F).)
Verify that if a carbon absorption system is being used that does not regenerate the carbon bed directly on-site in the control device, the existing carbon in the control device is replaced on a regular basis.
(NOTE: When to replace the carbon is determined by one of the following procedures:
-- a list of all information, references and sources used in preparing the documentation
-- records, including the dates of required compliance tests
-- design analysis, specifications, drawing, schematics, and piping and instrumentation diagrams if engineering calculations are used
-- when the carbon is replaced in carbon absorption systems
-- date and time when a control device is monitored for carbon breakthrough
Verify that records of monitoring operations and inspection information are kept for 3 years.
Verify that closed-vent systems designed and operated with no detectable emissions, as indicated by an instrument reading of less than 500 ppm above background, are monitored as follows:
-- visual inspection at least once a year for closed-vent system joints, seams, or other connections that are permanently or semi-permanently sealed (e.g., a welded joint between two sections of hard piping or a bolted and gasketed ducting flange)
-- whenever a component is repaired or replaced, monitor according to 40 CFR 265.1034(b)
-- annually and at times required by the regulatory agency for all other parts of the system using the procedures specified in 40 CFR 265.1034(b).
Verify that closed-vent systems designed to operate at no detectable emissions, as indicated by an instrument reading of less than 500 ppmv above background, are monitored as follows:
(NOTE: For closed-vent systems designed to operate at no detectable emissions, as indicated by an instrument reading of less than 500 ppmv above background, portions of the system designated as unsafe to monitor are exempt from the visual monitoring if:
Verify that detectable emissions, as indicated by visual inspection or by an instrument reading of greater than 500 ppmv above background, are controlled as soon as practicable but not later than 15 days after the emissions are detected.
Verify that a first attempt at repair is made no later than 5 calendar days after the emission is detected.
(NOTE: Delay of repair of a closed-vent system for which leaks have been detected is allowed if the repair is technically infeasible without a process unit shutdown, or if it is determined that the emissions resulting from the immediate repair would be greater than the fugitive emissions likely to result from delay of repair.)
Verify that closed-vent systems and control devices are operated at all times when emissions may be vented to them.
Verify that carbon removed from control devices that is a hazardous waste is managed in one of the following manners, regardless of the average VOC concentration of the carbon:
-- the unit has a final permit under 40 CFR 270 which implements the requirements of 40 CFR 264, subpart X
-- the unit is equipped with and operating air emission controls in accordance with applicable requirements
-- has a final permit under 40 CFR 270 which implements the requirements of 40 CFR 264, subpart O
-- has designed and operates the incinerator in accordance with the interim status required in 40 CFR 265, subpart O
-- has been issued a final permit under 40 CFR 270 implementing 40 CFR 266
-- has designed and operates the boiler or industrial furnace in accordance with the interim status requirements of 40 CFR 266, subpart H.
(NOTE: This section does not apply to (40 CFR 265.1050(d) and 265.1050(e)):
(NOTE: A leak is detected if there is an instrument reading of 10,000 ppm or greater or if there is an indication of liquid dripping from the pump seal.)
Verify that, when a leak is detected, the first attempt at repair is made within 5 calendar days and repair is completed within 15 calendar days.
(NOTE: Pumps equipped with dual mechanical seal systems and pumps designated for no detectable emissions that meet standards outlined here do not have to be monitored monthly or visually checked weekly.)
Verify that pumps equipped with a dual mechanical seal system which do not have to be monitored monthly or visually checked weekly, meet the following design and operation requirements:
(NOTE: Each owner or operator must determine, based on design considerations and operating experience, criteria that indicate failure of the seal system, the barrier fluid system, or both.)
Verify that pumps designated for no detectable emissions meet the following:
Verify that the compressor seal systems meet one of the following:
Verify that the barrier fluid is not a hazardous waste with organic concentrations 10 percent or greater by weight.
Verify that each barrier system is equipped with a sensor which will detect failure of the seal system, barrier fluid system, or both.
Verify that each sensor is checked daily or it is equipped with an audible alarm that is checked monthly.
(NOTE: Sensors on compressors located within the boundary of an unmanned site must be checked daily.)
(NOTE: Each owner or operator must determine, based on design considerations and operating experience, criteria that indicate failure of the seal system, the barrier fluid system, or both.)
Verify that, when a leak is detected, the first attempt at repair is made within 5 calendar days and the repair is made within 15 calendar days.
Verify that if there is a pressure release, the device is returned to a no detectable emission status within 5 calendar days and the device is monitored to ensure compliance.
(NOTE: Any pressure relief device that is equipped with a closed-vent system capable of capturing and transporting leakage from the pressure relief device to a control device is exempt from these requirements.)
Verify that each system collects the sample purge for return to the processing or for routing to the appropriate treatment system.
(NOTE: Gases displaced through filling of the sample container are not required to be collected or captured.)
Verify that each closed-purge, closed-loop system or closed-vent system does one of the following:
(NOTE: In-situ sampling systems are exempt from these requirements.)
Verify that the cap, blind flange, plug, or second valve seals the open end at all times, except during operations requiring hazardous waste stream flow through the open-ended valve or line.
Verify that each open-ended valve or line equipped with a second valve is operated so the valve on the hazardous waste stream end is closed before the second valve is closed.
Verify that, when a double block and bleed system is being used, the bleed valve is shut or plugged except during operations that require venting the line between the block valves.
(NOTE: A leak is detected if an instrument reading of 10,000 ppm or greater is measured. If a leak is not detected for 2 consecutive months, monitoring may be cut back to quarterly until a leak is detected.)
(NOTE: Valves that are designated for no detectable emissions, as indicated by an instrument reading of less than 500 ppm above background, do not have to be monitored monthly if:
(NOTE: Valves that are designated as unsafe to monitor are exempt from the requirement for monthly monitoring if:
(NOTE: Valves that are designated as difficult to monitor are exempt from the requirement for monthly monitoring if:
(NOTE: The following are alternatives to the prescribed monitoring schedule which can be used until the percentage of valves leaking is greater than 2 percent:
Verify that the first attempt at repairing a leak is done within 5 calendar days after detection and leak repair is completed within 15 calendar days after detection.
(NOTE: First attempts at repair include but are not limited to:
(NOTE: Any connector that is inaccessible or is ceramic or ceramic-lined is exempt from the monitoring requirements.)
(NOTE: A leak is detected if an instrument reading of 10,000 ppm or greater is measured.)
Verify that, when a leak is detected, the first attempt at repair occurs within 5 days and repair is done within 15 days after discovery.
(NOTE: First attempts at repair include, but are not limited to:
-- the instrument and operator identification numbers and the equipment identification number
-- the date evidence of a potential leak was found
-- the date the leak was detected and the date of each attempt to repair the leak
-- repair methods applied in each attempt
-- "Above 10,000" if the maximum instrument reading after each repair attempt is greater than 10,000 ppm
-- "Repair Delayed" and the reason for delay if the leak is not repaired within 15 calendar days after discovery
-- documentation supporting the delay of repair of a valve
-- signature of the owner or operator whose decision it was that the repair could not be effected without a hazardous waste management unit shutdown
-- the expected date of successful repair of the leak when it is not repaired within 15 calendar days
-- the date of the successful repair of the leak
-- a list of identification numbers for equipment (except welded fittings)
-- a list of identification numbers for equipment that the owner or operator elects to designate for no detectable emissions
-- a list of equipment identification numbers for pressure relief devices
-- the dates of required compliance tests, background levels, and maximum instrument reading measured during the compliance test
-- a list of identification numbers for equipment in vacuum service
-- identification either by list or location (area or group) of equipment that contains or contacts hazardous waste with an organic concentration of at least 10 percent by weight for less than 300 hours per calendar year.
Verify that the following information is kept for all valves subject to 40 CFR 265.1057(g) and (h):
-- a schedule of monitoring
-- the percent of valves found leaking in each monitoring period.
(NOTE: Any connector that is inaccessible or is ceramic or ceramic lined is exempt from the recordkeeping requirements.)
Verify that the following actions have been taken if the owner/operator has decided to comply with the 2 percent alternative:
Verify that if the owner/operator has decided to no longer comply with the 2 percent rule, the regulatory agency has been notified.
Verify that the satellite accumulation point is at or near the point of generation and is under the control of the operator of the waste generating process.
Verify that the containers are in good condition and are compatible with the waste stored in them and the containers are kept closed except when waste is being added or removed.
Verify that the containers are marked HAZARDOUS WASTE or other appropriate identification.
(NOTE: See Appendices A, B, C, D, and E for a guidance list of hazardous and acutely hazardous wastes.)
Verify by interviewing the shop managers that when waste is accumulated in excess of quantity limitations, the following actions are taken:
- The excess container is marked with the date the excess amount began accumulating
- The waste is transferred to a 90 day or permitted storage area within three days.
(NOTE: Any unidentified contents of solid waste containers and/or containers not in designated storage areas must be tested to determine if solid or hazardous waste requirements apply.)
- It is a completely enclosed, self-supporting structure that is designed and constructed of manmade materials of sufficient strength and thickness to support themselves, the waste contents, and any personnel and heavy equipment that operate within the unit
- It is designed to prevent failure due to pressure gradients, settlement, compression, or uplift, physical contact with the hazardous wastes, climatic conditions, and the stress of daily operations
- It has a primary barrier that is designed to be sufficiently durable to withstand the movement of personnel, wastes, and handling of equipment within the unit
- If the unit is used to manage liquids:
-- there is a primary barrier designed and constructed of materials to prevent migration of hazardous constituents into the barrier
-- there is a liquid collection system designed and constructed of materials to minimize the accumulation of liquid on the primary barrier
-- there is a secondary containment system designed and constructed of materials to prevent migration of hazardous constituents into the barrier, with a leak detection and liquid collection system capable of detecting, collecting, and removing leaks of hazardous constituents at the earliest practicable time
- It has controls sufficient to prevent fugitive dust emissions
- It is designed and operated to ensure containment and prevent the tracking of materials from the unit by personnel and equipment.
- It is completely enclosed with a floor, walls, and a roof to prevent exposure to the elements and to assure containment of wastes
- The floor and containment walls, including any required secondary containment system, are designed and constructed of man-made materials of sufficient strength and thickness to support themselves, the waste contents, and any personnel and heavy equipment that operate within the unit
- It is designed to prevent failure due to pressure gradients, settlement, compression, or uplift, physical contact with the hazardous wastes, climatic conditions, and the stress of daily operations
- It has sufficient structural strength to prevent collapse or other failure
- All surfaces in contact with hazardous wastes are compatible with the wastes
-- the primary barrier is sloped to drain liquids to the associated collection system
-- liquids and wastes are collected and removed to minimized hydraulic head on the containment system at the earliest practicable time
- The leak detection component of the secondary containment system meets the following:
-- it is constructed with a bottom slope of 1 percent or more
-- it is constructed of granular drainage materials with a hydraulic conductivity of 1 x 10 -2 cm/sec or more and a thickness of 12 inches (30.5 cm) or more, or constructed of synthetic or geonet drainage materials with a transmissivity of 3 x 10 -5 m 2 /sec or more
- If treatment is to be conducted in the building, the treatment area is designed to prevent the release of liquids, wet materials, or liquid aerosols to other portions of the building
- The secondary containment system is constructed of materials that are chemically resistant to the waste and liquids managed in the building and of sufficient strength and thickness to prevent collapse under pressure exerted by overlaying materials and by any equipment used.
(NOTE: An exception to the structural strength requirement may be made for lightweight doors and windows based on the nature of the waste management operations if the following criteria are met:
- The doors and windows provide an effective barrier again fugitive dust emissions
- The unit is designed and operated in a manner that ensures that the waste will not come in contact with the doors or windows.)
(NOTE: A containment building can serve as secondary containment systems for tanks within the building if it meets the requirements of 40 CFR 264.193(b), 264.193(c)(1) and (2), and 264.193(d).)
Verify that the following operational procedures are done:
- Controls and practices are used to ensure the containment of the waste within the building
- The primary barrier is maintained so that it is free of significant cracks, gaps, corrosion, or other deterioration that could cause hazardous waste to be released from the primary barrier
- The level of the stored/treated hazardous waste is maintained so that the height of any containment wall is not exceeded
- Measures are implemented to prevent the tracking of hazardous waste out of the unit by personnel or equipment used in the handling of the waste
- There is a designated area for the decontamination of equipment and collection of rinsate
- Any collected rinsate is managed as needed according to its constituents
- Measures are implemented to control fugitive dust emissions so that no openings exhibit visible emissions
Verify that data is gathered from monitoring equipment and leak detection equipment and the site is inspected at least once every seven days and the results recorded in the operating record.
Verify that there is a written description of procedures to ensure that waste does not remain in the building for more than 90 days.
Verify that there is documentation that the waste does not remain for more than 90 days.
Verify that when a leak is discovered:
- The discovery is recorded in the facility operating record
- Within seven days the regulatory agency is notified and within 14 working days written notice is provided to the regulatory agency
Verify that measures are taken to prevent the release of liquids or wet materials into areas without secondary containment.
Verify that a written description is maintained in the facilities operating log of operating procedures used to maintain the integrity of areas without secondary containment.
Verify that at closure, all waste residues, contaminated containment system components, contaminated subsoils, and structures and equipment contaminated with waste and leachate were removed or decontaminated.
Verify that the containment building is closed in accordance with closure and post-closure requirements for TSDFs.
Verify that if it is found that not all contaminated subsoils can be practicably removed or decontaminated, the site is closed and landfill post-closure requirements are implemented.
Determine if the facility generates restricted wastes by reviewing test results or reviewing procedures employed by facility management where process knowledge was applied in making the waste determination.
Verify that, for waste or soil which does not meet the applicable treatment standards or exceeds the applicable prohibition levels, the notice is issued and includes:
Verify that, for waste or contaminated soil which meets the treatment standard at the original point of generation, the notice includes:
Verify that, for restricted waste which is subject to an exemption from a prohibition of the type of land disposal used, the notice states that the waste is not prohibited from land disposal and includes:
(NOTE: Generators treating hazardous debris under the alternative treatment standards are not required to conduct waste analysis.)
Verify that the plan is kept on-site and:
Verify that if the facility has determined whether a waste is restricted using appropriate test methods, the waste analysis data is retained on-site.
Verify that if the facility has determined that they are managing a restricted waste that is excluded from the definition of a hazardous waste or solid waste or exempt from RCRA Subtitle C, a one-time notice is placed in the facility's files stating that the generated waste is excluded.
Verify that a copy of all notices, certifications, waste analysis data and other documentation is kept for at least three years from the date that the waste was last sent to an on-site or off-site TSDF.
- The name and address of the facility receiving the treated waste
- A description of the hazardous debris as initially generated, including the applicable EPA hazardous waste codes, treatability groups, and underlying hazardous constituents
- For excluded debris, the technology used to treat the debris.
Verify that the notification is updated if the debris is shipped to a different facility.
Verify that for debris that is excluded, if a different type of debris is treated or if a different technology is used to treat the debris, the notification is updated.
(NOTE: If the 90 day storage period is exceeded, the generator is required to be permitted as a TSDF.)
(NOTE: The prohibition on storage does not apply to hazardous wastes that have met treatment standards.)
Verify that liquid hazardous wastes containing PCBs at concentrations greater than 50 ppm are stored at a site that meets the requirements of 40 CFR 761.65(b) (see the Toxic Substances Control Act (TSCA)) and is removed from storage within one year of the date it was first placed into storage.
Determine if the facility transports hazardous waste off-site by using their own vehicles or a contractor.
Verify that the transporter has an EPA identification number.
Verify that all waste accepted, transported, or offered for transport is accompanied by a manifest.
Verify that prior to transport, the transporter signs and dates the manifest and returns a copy to the generator prior to leaving the facility.
Verify that the transporter retains a copy of the manifest after delivery.
Verify that all wastes accepted by the transporter are delivered to the designated facility listed on the manifest, or the alternate designated facility if an emergency prevents delivery, or the next designated transporter or the place outside the United States designated by the generator.
(NOTE: If the transporter cannot deliver the hazardous waste to the facilities or transporters designated on the manifest, the transporter must contact the generator for further directions and revise the manifest according to the generator's instructions.)
Verify that manifests are kept on file for three years.
(NOTE: Special issues involved in the transportation of hazardous waste by air, rail or water are not addressed in this guide.)
Inspect a sample of containers awaiting transport to verify that containers are properly constructed and exhibit no leaks, corrosion, or bulges.
Examine end-seams for minor weeping that indicates drum failure.
Verify that labeling and marking on each container is compatible with the manifests.
Verify that the following information is displayed on a random sample of containers of 110 gal. (416.40 L) or less in accordance with 49 CFR 172.304:
- Generator's name and address
- Manifest Document Number ____ .
Verify that proper DOT placarding is available for the transporter.
Verify that transporters give notice to the NRC and report in writing as required by 49 CFR 171.15 and 49 CFR 171.16.
Determine if drivers are trained in spill control procedures.
Determine if provisions have been made for securing wastes in vehicles during transport.
Verify the following:
- Transfer facility storage is for 10 days or less
- DOT packaging requirements are met
- Shipments are manifested and manifests accompany shipments
- Storage is consistent with good management practices.
(NOTE: Storage for more than 10 days will require a TSDF permit.)
Verify that transporters do not store manifested shipments of land disposal restricted wastes for more than 10 days (40 CFR 268.50(a)(3)).
(NOTE: The following countries have become OECD member countries since EPA promulgated its OECD regulations in 1996: South Korea, Czech Republic, Poland, and Hungary. EPA plans to amend its regulations to reflect these new OECD countries. In the interim, EPA strongly recommends that U.S. exports to these new OECD countries comply with the applicable OECD regulations, since these countries would expect compliance with OECD requirements for shipments they receive from the U.S.)
Determine whether the waste is destined for recovery operations, including resource recovery, recycling, reclamation, direct re-use or alternative uses.
Verify that 45 days prior to shipment of hazardous waste, the facility has notified EPA (in writing) of the following:
"I certify that the above information is complete and correct to the best of my knowledge. I also certify that legally-enforceable written contractual obligations have been entered into, and that any applicable insurance or other financial guarantees are or shall be in force covering the transfrontier movement."
(NOTE: The U.S. does not currently require financial assurance; however, U.S. exporters may be asked by other governments to provide and certify to such assurance as a condition of obtaining consent to a proposed movement.)
(NOTE: If wastes with similar physical and chemical characteristics, the same United Nations classification, and the same RCRA waste codes are to be sent to the same recovery facility by the same notifier, the notifier may submit one notification of intent to export these wastes in multiple shipments during a period of up to one year.)
For amber list wastes, verify that either (1) no objection was lodged by any exporting, importing, or transit countries within 30 days after issuance of the Acknowledgment of Receipt of notification by the competent authority of the importing country or (2) the competent authorities of all importing and transit countries provided written consent within 30 days.
For red list wastes, verify that written consent was received from the importing country and any transit countries prior to export.
Verify that contracts specify:
Verify that the tracking document includes all information contained in the notification and the following:
"I certify that the above information is complete and correct to the best of my knowledge. I also certify that legally-enforceable written contractual obligations have been entered into, and that any applicable insurance or other financial guarantees are or shall be in force covering the transfrontier movement, and that:
1. All necessary consents have been received; OR
2. The shipment is directed at a recovery facility within the OECD area and no objection has been received from any of the concerned countries within the 30 day tacit consent period; OR
3. The shipment is directed at a recovery facility pre-authorized for that type of waste within the OECD area; such an authorization has not been revoked, and no objection has been received from any of the concerned countries."
(NOTE: The notifier may delete sentences that are not applicable.)
and
Verify that a copy of the manifest is provided for delivery to the U.S. Customs official at the point of departure from the U.S.
Randomly check several annual reports to determine whether they contain the following information for all hazardous waste exported for recovery during the previous year:
"I certify under penalty of law that I have personally examined and am familiar with the information submitted in this and all attached documents, and that based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the submitted information is true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment."
Verify that 60 days prior to the initial shipment of hazardous waste to each country in each calendar year, the facility has notified the EPA (in writing) of the following:
-- identification of the hazardous waste shipped by EPA identification number
-- DOT shipping name, hazard class, and importer for the waste
-- estimated frequency/rate at which such wastes(s) is to be exported
-- estimated total quantity (in units)
-- all points of entry to and departure from each foreign country the waste will pass through
-- a description of the approximate length of time the waste will remain in each country, and how it will be handled there
-- the mode of transportation used to transport the waste and type(s) of containers used
-- description of the treatment, storage, or disposal method to be used in the receiving country
-- name and address of the foreign consignee.
Verify that a copy of this document was attached to the shipment.
Determine if there are any notations of discrepancies.
Determine if the following modifications are made by reviewing the manifest copies:
Verify that a copy of the manifest is provided for delivery to the U.S. Customs official at the U.S. point of departure.
- Notifies the EPA of a change in the conditions of the original notification to allow shipment to a new consignee and obtains an EPA Acknowledgment of Consent prior to delivery, or
- Instructs the transporter to return the waste to the primary exporter in the United States or designates another facility within the United States.
Verify that the facility instructs the transporter to revise the manifest to reflect changes made.
-- date of departure of the waste from the United States
-- place of departure of the waste from the United States
Verify that the Annual Reprts contain the following information for all hazardous waste exported during the previous calendar year:
- Type, EPA hazardous waste number, DOT hazard class and name for each hazardous waste(s) exported
- EPA identification number for each transporter (where applicable)
- Quantity of hazardous waste(s) exported
- Frequency (dates) of hazardous waste(s) exported
- Ultimate destination for all hazardous waste(s) exported
- Efforts used to reduce the volume and toxicity of the waste (and the changes achieved during the year in comparison to previous years)
"I certify under penalty of law that I have personally examined and am familiar with the information submitted in this and all attached documents, and that based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the submitted information is true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment."
- A copy of each notification of intent to export
- A copy of each EPA Acknowledgment of Consent
- A copy of each confirmation of delivery (signed manifests) of the waste
- Annual reports.
(NOTE: Periods of retention are automatically extended during the course of any unresolved enforcement action.)
(NOTE: The following countries have become OECD member countries since EPA promulgated its regulations in 1996: South Korea, Czech Republic, Poland, and Hungary. EPA plans to amend its regulations to reflect these new OECD countries. In the interim, EPA strongly recommends that exports to these new OECD countries comply with applicable OECD regulations, since these countries would expect compliance with OECD requirements for shipments they receive from the U.S.)
Determine whether the waste is for recovery operations, including resource recovery, recycling, reclamation, direct re-use or alternative uses.
Verify that contracts specify the name and EPA ID number, where available, of:
Verify that contracts specify:
Verify that the tracking document included all information contained in the notification and the following:
Determine if the following modifications are made by reviewing the manifest copies:
(NOTE: Notice of subsequent shipments of the same waste from the same foreign source is not required.)
Determine if the following modifications are made by reviewing the manifest copies:
(NOTE: Notice of subsequent shipments of the same waste from the same foreign source is not required.)
- The generator retains information that documents waste minimization activities.
- The program includes:
-- provisions for top management assurance that waste minimization is a company-wide effort
-- characterization of waste generation and waste management costs
-- periodic waste minimization assessments
-- a cost allocation system
-- encourages technology transfer
-- program implementation and evaluation
-- waste minimization employee awareness plans
-- adequate funding
-- clearly delineated roles both within the company and among each facility generating waste.
- Conclude if facility actions are resulting in the reduction of hazardous wastes.
(NOTE: Refer to Interim Final Guidance to Hazardous Waste Generators on the Elements of a Waste Minimization Program, 58 FR 31114, May 28, 1993.)
Ways to save money AND help the environment:
Save water AND money
with this showerhead adapter,
it lets the water flow until the water is hot, then shuts off water flow until you restart it, ShowerStart TSV Hot Water Standby Adapter
Protect your health with these:
Mattress Dust mite-Bedbug protector
, 100% Waterproof, Hypoallergenic, Zippered
Handheld Allergen Vacuum Cleaner with UV Sanitizing
for Allergies and Pet, Kills Mite, Virus, Molds, True HEPA with Powerful Suction removes Hair, Dander, Pollen, Dust
,
Immune Support
Supplement with Quercetin, Vitamin C, Zinc, Vitamin D3
GermGuardian Air Purifier with UV-C Light
and HEPA 13 Filter, R
emoves 99.97% of Pollutants
HEPA Air Purifier
, HEPA Air Cleaner with Washable Pre-Filter, AQI Display, ECO Mode, Sleep Mode, Pet Mode for Pets, Dust, Pollen, Removes 99.97% of Particles, Smoke, Mold, Pet Dander, Dust, Odors
Interesting Reads:
THE PREPPER'S CANNING & PRESERVING BIBLE:
[13 in 1] Your Path to Food Self-Sufficiency. Canning, Dehydrating, Fermenting, Pickling & More, Plus The Food Preservation Calendar for a Sustainable Pantry
The Backyard Homestead:
Produce all the food you need on just a quarter acre! P
aperback
The Citizens' Guide to Geologic Hazards:
A Guide to Understanding Geologic Hazards Including Asbestos, Radon, Swelling Soils, Earthquakes, Volcanoes
The Uninhabitable Earth:
Life After Warming
Book: The Sixth Extinction:
An Unnatural History Paperback
Environmental Health & Safety Online
EHSO ( Benivia, LLC
),
12850 Hwy 9, Suite 600-196, Atlanta, GA 30004 - Privacy Policy
Table of Contents to free guidance and resources: http://www.ehso.com/contents.php
Environmental and safety services for business - training, consulting, assessments, ISO14000, report and permit preparations and expert testimony:
http://www.ehso.com/EHSservices/enviserv.htmIf you provide environmental, safety, transportation, or related services or products; such as training, consulting, management, etc., EHSO would like to hear from you. We are looking for quality professionals to offer their services as affiliates. Please contact us via feedback .
Email:
How to get help with your questions
Copyright � 2015 Benivia, LLC (dba EHSO) All rights reserved.