Controls Contracting - Operations: Preconstruction What it takes to get the job?started!

Part 1 of 3

Steven R. Calabrese
Steven R. Calabrese
Control Engineering Corp.

Contributing Editor

T his is part one of a three-part series on controls contracting. This series focuses on the operations side of things, you know, the part that comes after the project is sold and turned over to the important people that make it happen, on schedule, within budget, and to the satisfaction of the customer! Seriously though, there is so much more to it than all that, and this series will barely scratch the surface, leaving out such matters as financial tasks, change orders, budget management, and so on. What this series will do, is give a basic outline of project tasks and milestones, from the preconstruction phase, through installation, to project closeout.

Articles
Interviews
Releases
New Products
Reviews
Editorial

[an error occurred while processing this directive]

Coming Events
Sponsors
Site Search
Blogs
Archives
Past Issues
Home

[an error occurred while processing this directive]

Understanding Mechanical Plans

Now that you have the plans and specs, and a basic understanding of the scope of the project, it?s time to get busy! Get yourself a set of highlighters, and start coloring the plans. Seriously. Or if you?re like me with a couple of creative kids of that age, have them help you! Begin by going through all of the floor plans and highlighting all of the equipment tags. These are the familiar six-sided bisected polygons that have letters in the top half to designate an equipment abbreviation (i.e., AHU for air handling unit), and numbers in the bottom half to give a unique tag to each and every piece of equipment (we hope!). The choice is yours, but I typically use yellow for highlighting equipment tags, and for any important notes that need to be flagged. Follow that up by highlighting all of the equipment associated with the tags. Again the choice is yours, but since orange is seemingly the most popular highlighter available aside from yellow (why is this??), I use orange for equipment. From there I use other colors to highlight control items that are shown on the plans (thermostats, sensors, dampers and actuators, etc), and to highlight pipe and duct systems as required.

Highlight the general notes and the key notes on each mechanical plan, as well as other miscellaneous notes that pertain to the controls. Next, go to the details sheets and scour the individual details for items that you?ll need to account for. There?s a tendency to skim over the details sheets (at least by me), however there?s usually some info ?hidden? there that you?ll need to know, that might not be accounted for anywhere else. If there are piping schematics and/or ventilation riser diagrams, give these some well-deserved attention, as they tell their own story on how the systems are laid out and are designed to operate. Finally, turn your attention to the equipment schedules, and take note of equipment counts, making sure that they match your investigation of what?s actually on the mechanical plans. For each schedule, highlight important equipment attributes that you may need to have knowledge of for the engineering phase of your project. Items such as CFMs, GPMs, design temperatures, and electrical characteristics, hold a lot of value and tell a lot about how these mechanical systems are to operate, individually, and even interdependently.

If you?re fortunate enough to actually have equipment control schematic diagrams included on the mechanical plans, then these are your design documents, that will provide the basic structure on how you will proceed to generate your submittal package (control drawings, sequences, etc.).

If control schematics are not included as part of the design documents, then you?ll be required to rely heavily on the written specification. Either way, you need to study the spec and highlight the important stuff. Go through each major section of the controls portions of the spec, and flag all of the items that directly apply to the control systems design. Chances are that you?ll be using ?a lotta yellow? here, as this is where you?ll find most of what pertains to the design and operational intents of the various mechanical systems, from a controls standpoint. Typically included are product and device specs, sequences of operation, and points lists. All of the information required to perform the hardware (and software) design of the control systems.

Once everything is highlighted and you?ve gotten a firm grasp on the scope of the project (virtually through osmosis), it?s time to start the next phase. If you have not adequately completed the above tasks, then go no further, turn back, and get it done! Nothing like jumpstarting the engineering halfway through this phase, only to get off to a false start and having to begin from scratch. Take it from me: it pays to take the time to understand the project thoroughly before you begin to tackle the engineering. If you?ve gotten through all of the above, then go get a drink of water, and please proceed to the next heading.

[an error occurred while processing this directive] Engineering from Start to Finish

That last section was pretty lengthy?this one in comparison should be longer, but as I?m running out of room it?ll actually be somewhat shorter (thank goodness!). Anyway, now that you have a grip on the project, thus begins the task of ?submittal generation?. Start by creating schedules for control valves, motorized dampers, and airflow measuring stations (as the job dictates). These schedules are to include information pertaining to the size, selection, application, and performance criteria of the items. Most controls contractors have standard spreadsheets that they?ve developed for putting together these schedules.

Now create sketches for the mechanical systems, and for each piece of individually controlled equipment. Add in the required sensors and transmitters (temperature, pressure, humidity, etc.), switches and two-state controllers (fan/pump status switches, safeties and limits?), and end devices (control valves, motorized dampers, VFDs, etc.), using the specified sequences, points lists, and control schematics (if provided) to account for all required components. From there, build the project-wide Bill of Materials, another spreadsheet that contains all of the unique components selected for the project.

With the above task completed, now determine the required I/O (inputs/outputs) for each system and each piece of equipment, and make your controller selections accordingly. Using your method of choice, develop point-to-point wiring diagrams for each. Organize your drawings in a sensible manner, and include the specified points lists for each system, as re-iterated from the specifications and expanded upon and/or modified to suit your design.

If the project is specified to be networked DDC (Direct Digital Control), show a ?riser diagram? illustrating how all of the individual controllers are networked together to form the Building Automation System (BAS).

Package the drawings along with the written sequences and device data sheets, in a binder and send them off to the consulting engineer for their ?seal of approval?, or the dreaded ?revise as noted? stamp. Make your corrections as required, and move on to the next phase of the project?installation (next month).