Lees Corner Elementary Capital Project
Information about the Renovations
The Lees Corner Elementary Schoo l project was identified as part of the 2008 Renovation Queue, which was approved by the Fairfax County School Board (FCSB) in 2009 . Lees Corner Elementary ranks 48th out of 63 schools on the list. Planning and design efforts for the renovation were funded through the 2021 School Bond Referendum, with construction funding provided by the 2023 School Bond Referendum.
Upon completion, the project will modernize and reimagine the school, providing updated learning environments and fully upgraded mechanical, electrical, and plumbing systems. The renovation will also expand the building by approximately 32,974 square feet, including the relocation of the existing windowless administrative offices to exterior walls to improve visibility of the school entrance and bus loop and main entry. A major component of the expansion are the addition of a two-story classroom wings and partial expansion of the cafeteria.
Site improvements will enhance both safety and functionality, including updates to the bus loop, an extended Kiss & Ride area, new playgrounds, and expanded outdoor classroom spaces. Once completed, Bonnie Brae School will total approximately 126,499 Gross Square Feet and will be designed to meet the Virginia Collaborative for High Performance Schools (CHPS) Designed certification standards, supporting a healthy, sustainable, and energy-efficient learning environment.
We appreciate your patience and support as we work to improve our school facilities. Stay tuned for more updates.
Latest Update: November 13, 2025
Construction Information
Construction continues to move forward with exciting progress throughout the school.
-
Classroom & Library Additions
The new classroom addition on the west end of the building is taking shape, while on the north side the new library and additional classrooms are progressing well.
- Gym upgrades, including a new floor and new equipment. (Final gym lines are forthcoming.)
-
Administrative & Cafeteria Expansion
Expansion of the administrative office area and the cafeteria is visible and accessible through the newly constructed Door 1.
-
Playground & Accessibility Improvements
The new ramp around the school-age playground now connects the classroom trailers to the main school building. The playground itself is already in use and receiving great feedback from students and staff.
Two expanded asphalt paths at the east end of the building coming from the neighborhoods.
The new kiss and rideis complete improving access at arrivals and dismissals.
The new retaining walls at the north side of the school and surrounding the school age playground and (coming soon) basketball courts are complete.
-
Trailer Restroom Facilities
A larger restroom trailer has been installed, replacing the two smaller restroom trailers used last school year, providing more convenience for students and staff.
-
Main Entry and Canopy: Work continues at the new main entry at Door 1, including installation of the new entry canopy.
-
Cafeteria Expansion: Construction continues at the front of the school to enlarge and improve the cafeteria.
-
Demolition: Interior demolition has begun in classrooms on both the first and second floors at the front and rear of the school.
- Mechanical, Electrical, and Plumbing (MEP) Updates: Upgrades to building systems are underway, with new electrical, domestic water, and sanitary lines installed and connected in the classrooms at the front and rear
ADA-accessible temporary classrooms and restrooms learning complex installed. Temporary education village fenced enclosure complete. New utilities for temporary education village are complete
- Phased Occupied Building: Students and Construction activities and workers are separated.
- Additional classrooms
- Renovated classrooms
- Sustainability Improvements: The renovation will feature a more sustainable building with all LED lighting and advanced lighting controls.
- HVAC System: A new, more efficient HVAC system with updated controls will enhance comfort and energy efficiency.
- Technology Upgrades: We are incorporating updated technology to support modern learning environments.
- Life Safety Upgrades: New fire alarm system, new security system, fire sprinkler system, and new generator.
- Water Conservation: Automatic low-flow sinks, toilets, and urinals will be installed to promote water conservation.
- Daylighting: New windows and improved natural lighting in classrooms and gymnasium.
- Kitchen and Expanded cafeteria: All new kitchen equipment and expanded cafeteria.
- Relocated and Improved: SACC, Library, music, and art.
- Various site improvements:
- New pre-K playground
- New school-age playground
- New outdoor basketball courts
- Improved kiss and ride circulation
- Additional parking
Lees Corner School Renovation Gallery
Engagement Opportunities
Information on community meetings will be posted here once they are planned.
Future Events
Lees Corner Elementary School continues to make progress on its renovation project. You are invited to attend an End-of-Phase Community Meeting on Monday, May 19, from 6–7 p.m. in the Lees Corner Elementary School cafeteria. Language interpretation services will be available.
During the meeting, Fairfax County Public Schools staff will provide updates on the completed phase of the project. Lees Corner Elementary school has completed Phase 2 of the renovation. This is the five classroom addition to the west and the north addition consisting of four classrooms including two new art spaces with a kiln room along with two new SACC room's and a new administrative space.
Community members will also can ask questions and learn more about the next steps of the project.
For updates, join the FCPS News You Choose subscription for this project. Once signed up or logged in, choose the Capital Projects (School Construction) and the school's construction topic.
Key Build Information
Funding: 2021 Bond (Planning/Design), 2023 Bond (Construction)
Future Building Area: 118,248 SF
Anticipated Future Capacity:900 students
Building Area: 81,843 SF
Acreage: 13.9
Prior Renovation: n/a
Prior Capacity Enhancement: n/a
Renovation Queue Rank: #48
Architect: Grimm+Parker
Contractor: Henley Construction
Current Status: Under Construction
Start of Construction: January 2025
Estimated Completion: July 2027
School Information
Address: 13500 Hollinger Ave, Fairfax, VA 22033
FCPS Region: 5
Grades: K-6
HS Pyramid: Chantilly HS
MS Feeder: Franklin MS
Opened: 1987
Programs: AAP Local Level IV, Autism, Intellectual Disabilities, SACC (1 classroom)
Past Engagement, Planning & Construction Information
January 30, 2025: Pre-Construction Meeting
October 4, 2023: Fairfax County Planning Commission Meeting
July 17, 2023 7:00 p.m.: Sully District Land Use Committee Meeting
- Address:
Sully District Governmental Center
4900 Stonecroft Blvd.
Chantilly VA 20151 - Presentation (July 2023)
March 29, 2023:Community Meeting
September 22, 2022:Design Feedback and Engagement Committee meeting #2
May 26, 2022:Design Feedback and Engagement Committee meeting #1