Crossfield Elementary Capital Project
Information about the Renovations and Additions
The Crossfield Elementary School project was identified as part of the 2008 Renovation Queue, which was approved by the Fairfax County School Board (FCSB) in 2009 . Crossfield Elementary ranks 42 out of 63 schools on the list. Planning and design efforts for the renovation were funded through the 2019 School Bond Referendum, with construction funding provided by the 2021 School Bond Referendum.
Upon completion, the project will modernize the school facility, providing enhanced learning environments and fully upgrade mechanical, electrical, and plumbing systems. The renovation will also expand the building by approximately 11,638 square feet, including a partial addition to the administrative offices and main entrance to improve visual oversight of the site and bus loop.
Site improvements will enhance both safety and functionality, including updates to the bus loop, an extended Kiss & Ride area, new playgrounds, and expanded outdoor classroom spaces. Once completed, Crossfield Elementary School will total approximately 100,814 Gross Square Feet and will be designed to meet the Virginia Collaborative for High Performance Schools (CHPS) Designed certification standards, supporting a healthy, sustainable, and energy-efficient learning environment.
The Collaborative for High Performance Schools (CHPS) recognizes Crossfield Elementary School Renovation and Additions as a high-performance learning environment that has earned CHPS Designed status under the VA-CHPS 2011 criteria. Crossfield Elementary School Renovation and Additions has achieved the necessary prerequisites and credits to be recognized as a CHPS Designed School. The project earned 44 points exceeding the threshold for a renovation with an addition project. CHPS is pleased to welcome Crossfield Elementary School Renovation and Additions to the distinguished rank of education facilities that are leading the movement to build this new generation of healthy, high performance, green schools.
Latest Update: March 19, 2026
Construction Information
- Regrading and fresh landscaping
- New irrigation system & sod in upper athletic field.
- Sports field with baseball/softball diamond
- New backstoр
- New stairs and switchback to trailers.
- New addition with additional classrooms, work rooms, pull out spaces .
- New classrooms in area B.
- New and expanded library.
- New and expanded administrative area.
- New kitchen and kitchen equipment.
- New finishes in cafeteria.
- New elevator.
- New windows and improved daylighting in area B turned over spaces.
- New asphalt paving.
- New pervious pavers for parking, improving storm water management practices.
-
Renovation & Expansion Complete
We're thrilled to announce that all major renovations and additions are now substantially complete! Students are learning together in a bright, modernized buliding, and the temporary classrooms ('The Launchpad') are being removed.
- What's New Inside?
- Fully renovated interiors with fresh finishes
- New classrooms, art rooms, and a dedicatd kiin & kiln room
- A brand-new kitchen and inviting library
- Expanded windows for better daylight in classrooms
- Solar skylights in the gym for natural lighting
- Energy & Sustainability Upgrades
- New enclosed courtyard from library/classroom addition
- Outdoor classroom with planter beds, seating, and sink
- Cistern system to reuse roof runoff water
We appreciate our community 's continued support in building a safe, sustainable, and inspiring learning space for every student.
- Sustainability Improvements: The renovation will be a more sustainable building with all LED lighting and advanced lighting controls.
- HVAC System: A new, more efficient HVAC system with updated controls will enhance comfort and energy efficiency.
- Technology Upgrades: We are incorporating updated technology to support modern learning environments.
- Life Safety Upgrades: New fire alarm system, new security system, fire sprinkler system, and new generator.
- Water Conservation: Automatic low-flow sinks, toilets, and urinals will be installed to promote water conservation.
- Daylighting: New windows and improved natural lighting in classrooms and gymnasium.
- Kitchen and Expanded cafeteria: All new kitchen equipment and expanded cafeteria.
- Relocated and Improved: SACC, Library, music, and art.
- Various site improvements:
- New pre-K playground
- New school-age playground
- New outdoor basketball courts
- Improved kiss and ride circulation
- Additional parking
Future Events
Information on community meetings will be posted here once they are planned.
For updates, join the FCPS News You Choose subscription for this project. Once signed up or logged in, choose the Capital Projects (School Construction) and the school's construction topic.
Key Build Information
Funding: 2019 Bond (Planning), 2021 Bond (Construction)
Future Building Area: 100,815 SF
Anticipated Future Capacity: 750
Building Area: 89,134 SF
Acreage: 14.20
Prior Renovation: n/a
Prior Capacity Enhancement:n/a
2008 Renovation Rank: #42
Architect: Moseley Architects
Contractor: R.J. Crowley
Current Status: Under Construction
Start of Construction: February 2023
Estimated Completion: June 2025
School Information
Address: 2791 Fox Mill Road, Herndon, VA 20171
FCPS Region: 1
Grades: K-6
HS Pyramid: Oakton HS (split feeders: South Lakes HS, Chantilly HS)
MS Feeder: Carson MS, Hughes MS, Franklin MS
Opened: 1988
Title 1: No
K-3 Cap: n/a
Programs: AAP Local Level IV, Early Childhood Class Based, Autism, SACC (2 Classrooms)
Past Engagement, Planning & Construction Information
April 29, 2025: Community Meeting
February 9, 2023: School Board Meeting agenda item - Decision on construction contract.
February 8, 2023: PTO Open Meeting 6:30 p.m. in the school cafeteria. All school community members are welcome to attend. FCPS Design and Construction will present an update on the renovation at 7 p.m.
January 12, 2023:School Board Meeting agenda item - Information regarding construction contract.
- Meeting Agenda (January 2023) New Business Item 7.03 Award of Contract
April 27, 2022: Community Meeting
April 14, 2022: PTO Meeting
September 21, 2021: Hunter Mill Land Use Committee
November 23, 2020: Design Feedback and Engagement Committee meeting #1