Stardust Power Inc (SDST) Q1 2026 Earnings Call Highlights: Strategic Advances Amid Financial ...

This article first appeared on GuruFocus .

Release Date: May 14, 2026

For the complete transcript of the earnings call, please refer to the full earnings call transcript .

Positive Points

  • Stardust Power Inc ( NASDAQ:SDST ) has secured a minor source air quality construction permit, allowing construction of the Muskogee refinery to commence once financing is secured.

  • The company completed its FEL-3 study, defining the technical scope, cost framework, and execution plan for the project, supported by an independent third-party review.

  • Stardust Power Inc ( NASDAQ:SDST ) has advanced its feedstock supply with multiple LOI agreements, reducing dependence on single-asset supply risk.

  • The company has secured access to up to $15 million in an equity financing facility and announced a letter of intent for up to $150 million in project-level financing.

  • Stardust Power Inc ( NASDAQ:SDST ) has joined the Cornerstone Consortium and the Lithium Regional Innovation Cluster, enhancing its engagement with industry, government, and technology partners.

Negative Points

  • Stardust Power Inc ( NASDAQ:SDST ) remains pre-revenue, with its financial performance dependent on future capital raising efforts.

  • The company reported a net loss of $5.2 million for Q1 2026, an increase from $3.8 million in the same period the previous year.

  • Operating cash usage totaled $2.1 million for the quarter, indicating ongoing cash flow challenges.

  • The company's ability to meet working capital and capital expenditure requirements over the next 12 months is contingent on raising additional capital.

  • Net cash used in financing activities was minimal at $4,000 for the current quarter, reflecting limited new capital inflows.

Q & A Highlights

Q: What are the key milestones achieved by Stardust Power in Q1 2026? A: Roshan Pajari, CEO, highlighted that Stardust Power has secured a minor source air quality construction permit, completed the FEL-3 study, and advanced feedstock supply with multiple LOI agreements. These milestones position the project for financing and execution, particularly for the Muskogee Lithium Refinery.

Q: How is Stardust Power addressing the U.S. lithium supply chain constraints? A: Roshan Pajari, CEO, stated that the constraint is not resource availability but refining capacity. The Muskogee refinery aims to address this gap by enhancing refining capacity, thus strengthening the domestic lithium supply chain.

Q: What is the financial strategy for the Muskogee Refinery project? A: Uday Divasper, CFO, explained that the majority of the capital required for the refinery will be raised at the project level to align capital with the asset, optimize the capital structure, and limit dilution for public shareholders. The project is eligible for a higher debt component, ranging from 70% to 80% of total funding needs.

Q: What are the financial results for Q1 2026? A: Uday Divasper, CFO, reported a net loss of $5.2 million, compared to $3.8 million in the prior year. Despite the higher net loss, operating cash usage improved due to disciplined cost controls and favorable timing of working capital activity.

Q: What are Stardust Power's near-term priorities? A: Roshan Pajari, CEO, emphasized that the focus is on advancing project-level financing to move the refinery into construction, progressing EPC planning, and ensuring readiness for long-term operational execution.

For the complete transcript of the earnings call, please refer to the full earnings call transcript .